0

Delhi High Court’s Jurisdictional Ruling: Venue vs Seat of Arbitration and Time Extension for Arbitral Proceedings

Title:  Reliance Infrastructure Limited v. Madhyanchal Vidyut Vitran Nigam Limited

Decided on:  14th August, 2023

+  O.M.P.(MISC.)(COMM.) 161/2020 and IA No. 9377/2020

CORAM: HON’BLE MR. JUSTICE SACHIN DATTA

Introduction

The Delhi High Court recently rendered a significant decision regarding the distinction between the ‘venue’ and ‘seat’ of arbitration, as well as the extension of time for completing arbitral proceedings. The case involved a petition seeking an extension of time for issuing an arbitral award under Section 29A(4) and (5) of the Arbitration and Conciliation Act, 1996.

Facts

The petitioner, a participant in Rural Electrification works in Uttar Pradesh, initiated arbitration proceedings due to disputes arising from contracts. The General Conditions of Contract (GCC) mentioned that disputes would be resolved through arbitration, with Delhi having exclusive jurisdiction. Subsequently, the petitioner sought an extension for the Sole Arbitrator to issue the arbitral award.

Analysis

The central issue before the Court was the distinction between the ‘venue’ and ‘seat’ of arbitration and the significance of an exclusive jurisdiction clause. The Court underscored that when an arbitration clause designates a specific ‘venue,’ it essentially anchors the arbitral proceedings to that location, making it the ‘seat’ of arbitration. Thus, the Court exercising supervisory jurisdiction over the designated ‘venue’ becomes the supervisory authority for the arbitral process, even if a general exclusive jurisdiction clause exists for a different court. The Court examined various judgments and legal precedents to establish this principle.

The Court highlighted the fact that the LOA’s ‘exclusive jurisdiction’ clause was general and did not specifically pertain to arbitration, while the GCC Clause 48.1.2 designating Delhi as the ‘venue’ of arbitration took precedence. This reinforced Delhi as the ‘seat’ of arbitration. The Court clarified that the Arbitration Act empowers courts to extend the Arbitrator’s mandate even after the award’s deadline, upon sufficient cause shown.

Held

The Court declared its territorial jurisdiction over the arbitration proceedings and the petition’s maintainability. It granted the petition, allowing an extension of one year from the date of the judgment for completing the arbitration proceedings and issuing the arbitral award. The Court emphasized that the Sole Arbitrator had not shown any lack of expedition in the proceedings.

Conclusion

The Delhi High Court’s ruling highlights the significance of accurately designating the ‘seat’ of arbitration based on the specified ‘venue’ and clarifies that exclusive jurisdiction clauses do not undermine the seat’s authority. The Court’s decision also underscores the flexibility of the Arbitration Act to grant extensions for arbitral proceedings.

“PRIME LEGAL is a full-service law firm that has won a National Award and has more than 20 years of experience in an array of sectors and practice areas. Prime legal fall into a category of best law firm, best lawyer, best family lawyer, best divorce lawyer, best divorce law firm, best criminal lawyer, best criminal law firm, best consumer lawyer, best civil lawyer.”

Written by- Ankit Kaushik

Click here to view judgement

0

If there’s an admitted liability, a dispute concerning unpaid amounts cannot be directed to arbitration.

PUNJAB & HARYANA HIGH COURT

M/s Simplex Infrastructure Limited and another

 Vs.

 M/s J.P.Singla Engineers and Contractor

CR 6634/2019

Coram HON’BLE MS. JUSTICE NIDHI GUPTA

FACTS:

The current revision petition has been submitted to contest the decision dated 5.9.2019 (Attachment P-5) issued by the Civil Judge (Junior Division) in Chandigarh. This decision pertains to the rejection of the applicants’ petition under Section 8 of the Arbitration and Conciliation Act, 1996 (referred to as ‘the 1996 Act’). The respondent, a sole proprietorship firm engaged in construction, was contracted by the petitioners for road construction via an Agreement/work order from 14.4.2014. The respondent completed the project according to specifications and submitted bills for the period up to 22.8.2016. A final bill for minor patch work on 13.5.2017 was also sent. However, payment was not received despite reminders, leading the respondent to file Civil Suit No. 2207 of 2018 seeking to recover Rs. 27,16,659/- as principal and Rs. 3,79,748/- as 15% per annum interest from 13.5.2017. The petitioners, as defendants, argued the civil suit was improper due to Clause 12 of the Agreement/work order, which mandated arbitration for disputes. They submitted an application under Section 8 of the 1996 Act to this effect, which was rejected by the Civil Judge (Junior Division) on 5.9.2019. The petitioners have lodged the current revision petition to challenge this ruling.

COURT ANALYSIS AND DECISION:

The arbitration clause applies when a dispute falls within the scope of an Arbitration Agreement. In this case, the dispute doesn’t pertain to the execution, completion of work, or the contract itself. Instead, it concerns uncompensated dues. It’s not a dispute “under,” “in connection with,” or “regarding” the contract. Consequently, arbitration isn’t suitable, and the respondent, who is entitled to their dues, has appropriately filed a recovery suit. The respondent attempted to settle amicably, but the petitioners didn’t respond. Given these circumstances, the order dated 5.9.2019, which dismissed the revision petition, is deemed correct and the revision petition is rejected.

“PRIME LEGAL is a full-service law firm that has won a National Award and has more than 20 years of experience in an array of sectors and practice areas. Prime legal fall into a category of best law firm, best lawyer, best family lawyer, best divorce lawyer, best divorce law firm, best criminal lawyer, best criminal law firm, best consumer lawyer, best civil lawyer.”

Written by- Srijan Garg

simplex-infrastructure-ltd-anr-versus-jp-singla-engineers-451752