1

“Decision of Arbitral Tribunal to not Implead a Party to Arbitration is not an Interim Award”: Delhi High Court

Case title: National Highway Authority of India v. Ms IRB Ahmedabad Vadodra Super Express Tollways Pvt. Ltd

Case no.: O.M.P. (COMM) 455/2022 & I.A. 18565/2022

Order on: 2nd April 2024

Quorum: Justice Prateek Jalan

FACTS OF THE CASE

The petitioner, National Highway Authority of India (NHAI), challenged a decision of a three-member Arbitral Tribunal dated 01.08.2022. This decision rejected NHAI’s application under Order I Rule 10 of the Code of Civil Procedure, 1908 (CPC) for impleadment of the State of Gujarat as a party to the arbitral proceedings. The arbitral proceedings stemmed from a Concession Agreement dated 25.07.2011 between NHAI and the respondent, MS IRB Ahmedabad Vadodra Super Express Tollways Pvt. Ltd.

CONTENTIONS OF THE APPELLANT

Advocates Mr. Ankur Mittal, Mr. Abhay Gupta, and Mr. Ankur Saboo represented NHAI. They argued that the State of Gujarat should be impleaded based on the obligations it undertook in a State Support Agreement dated 11.02.2016, which was related to the Concession Agreement.

CONTENTIONS OF THE RESPONDENTS

Represented by Mr. Atul Nanda, Senior Advocate, the respondent contested NHAI’s application for impleadment, arguing that the Arbitral Tribunal lacked jurisdiction to decide on the impleadment of the State of Gujarat.

Mr. Nanda submits that the question of maintainability of a petition under Section 34 of the Act against an order of an arbitral tribunal declining impleadment of a third party is no longer res integra. He relies upon the decision in National Highway Authority of India vs. Lucknow Sitapur Expressway Ltd. (Lucknow Sitapur Expressway), The Court was, in that case, also concerned with a decision of an arbitral tribunal adjudicating disputes under a Concession Agreement. The Tribunal had rejected an application by NHAI for impleadment of a State Government on the ground that it was a party to a State Support Agreement.

LEGAL PROVISIONS

Section 34 of the Arbitration and Conciliation Act, 1996 – Application for setting aside arbitral award.

It allows parties to challenge an arbitral award before the appropriate court on certain grounds, including that the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties. In this case, the petitioner NHAI, invoked Section 34 to challenge the decision of the Arbitral Tribunal rejecting its application for impleadment of the State of Gujarat.

ISSUE

The main issue was whether the decision of the Arbitral Tribunal rejecting NHAI’s application for impleadment of the State of Gujarat constituted an arbitral award, thus making it amenable to challenge under Section 34 of the Arbitration and Conciliation Act, 1996.

COURT’S ANALYSIS AND JUDGEMENT

The court examined precedents, including the case of Lucknow Sitapur Expressway Ltd., which involved similar circumstances. In Lucknow Sitapur Expressway, it was ruled that a decision rejecting an application for impleadment did not constitute an arbitral award under Section 2(1)(c) of the Act. The court emphasized that for a decision to be considered an award, it must decide a substantive dispute or conclusively settle an issue pertaining to the heart of the dispute.

The court further clarified that the distinction between a decision on jurisdiction and one on merits did not affect the characterization of the decision as an award. Even if the tribunal ruled on the jurisdiction to decide on impleadment, it did not change the nature of the decision. The court referenced various legal principles and previous judgments to support its conclusion.

In light of the precedent set by Lucknow Sitapur Expressway and other relevant judgments, the court held that NHAI’s petition under Section 34 of the Act was not maintainable. Consequently, the petition was dismissed, and all pending applications were disposed of.

The court’s decision in the case of O.M.P. (COMM) 455/2022 reaffirmed the legal position established by precedent, particularly the Lucknow Sitapur Expressway case. It clarified the criteria for a decision to be considered an arbitral award and emphasized that decisions on procedural matters like impleadment did not fall under this category.

“PRIME LEGAL is a full-service law firm that has won a National Award and has more than 20 years of experience in an array of sectors and practice areas. Prime legal fall into a category of best law firm, best lawyer, best family lawyer, best divorce lawyer, best divorce law firm, best criminal lawyer, best criminal law firm, best consumer lawyer, best civil lawyer.”

Judgement Reviewed by – Chiraag K A

Click here to View Judgement

0

Delhi Metro Rail Corporation is directed to pay damages for delay to MBL Infrastructures Ltd. despite no specific clause in Agreement: Delhi High Court

Case Title: MBL Infrastructures Limited v. Delhi Metro Rail Corporation

Case No: O.M.P. (COMM) 311/2021

Decided on:  12th December, 2023

CORAM: THE HON’BLE MR. JUSTICE CHANDRA DHARI SINGH 

Facts of the Case

MBL Infrastructure Ltd., a Public Limited Company with expertise in Civil Engineering projects throughout India, and the Delhi Metro Railway Corporation, a joint venture of the Government of NCT of Delhi and the Government of India, entered into a contract. This agreement focused on the construction of Sarai Station, encompassing architectural finishing, water supply, sanitary installations, external development works, and structural works on the Badarpur – Faridabad Corridor within Delhi MRTS Phase III.

The Respondent issued an invitation for tenders for the project on March 9, 2012. On the same day, the Petitioner submitted its tender, which was subsequently accepted by the Respondent on May 9, 2012. The project, valued at Rs. 41.57 crores, was scheduled to commence on May 21, 2012, and conclude on November 20, 2013, encompassing an 18-month duration.

The Petitioner furnished performance bank guarantees and bank guarantees for mobilization advance. Despite encountering delays in the site handover process, the Petitioner received the initial mobilization advance installment on September 6, 2012. However, the Respondent denied possession of the remaining plot designated for Sarai Metro Station. Following this, the Respondent issued a notice, alleging the Petitioner’s failure to meet work program commitments and other obligations. Despite the Petitioner’s assertion of timely performance, the Respondent terminated the contract on November 1, 2013, and invoked the bank guarantees provided by the Petitioner.

Following arbitration, the Arbitral Tribunal rendered its award on March 6, 2020, determining that the Respondent had breached the contract and was accountable for the project delay. While the Tribunal upheld some of the Petitioner’s claims, it dismissed others, including all Counter claims presented by the Respondent. Notably, the Tribunal deemed the termination of the contract and the encashment of the Performance Bank Guarantee as illegal and unjustified, considering the Respondent’s breach of the agreement. Expressing dissatisfaction with the rejection of certain claims, the Petitioner contested the award, specifically challenging the tribunal’s decision to dismiss those claims.

Legal Provision

Section 34 (2) of the Arbitration and Conciliation Act states that an arbitral award may be set aside by the Court only if-

  1. the party making the application 1[establishes on the basis of the record of the arbitral tribunal that]–
  2. a party was under some incapacity, or
  3. the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or
  • the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or
  1. the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration:

Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or

  1. the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this Part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or
  2. the Court finds that-
  3. the subject-matter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or
  4. the arbitral award is in conflict with the public policy of India.

Issues

  1. Whether the tribunal, despite recognizing the petitioner’s incurred expenses and the harm resulting from the respondent’s actions, refrained from awarding damages, costs, and interest?
  2. Whether the denial of damages by the tribunal contradicts Section 55 and 73 of the Indian Contract Act?

Court’s analysis and decision

The Delhi High Court emphasized that it can only interfere with the arbitral award if the grounds under Section 34 of the Arbitration and Conciliation Act are made out and not otherwise.

The court noted the tribunal’s determination of the respondents being accountable for the project work delay and the illegal nature of the termination. Highlighting that the tribunal attributed the delay to the respondent, leading to damages suffered by the petitioner, the court asserted that in such a scenario, the tribunal should have granted damages to the petitioner.

The court ruled that the arbitral tribunal, despite the existence of Clause 8.3 in the GCC limiting remedies to a time extension, cannot deny damages. It emphasized that such a clause does not restrict the tribunal’s authority to award damages, particularly in light of Section 55 and 73 of the Indian Contract Act.

Additionally, the court declared that any clause limiting the aggrieved party’s right to claim damages is against the fundamental policy of Indian Law. It affirmed that such a prohibitionary clause doesn’t hinder the tribunal’s power to compensate a party for losses due to the other party’s delay, even if the contract only provides for an extension of time.

The court clarified that the arbitral tribunal can grant damages for delay even if the contract only allows for an extension of time as the remedy for the contractor. Once the tribunal establishes the employer’s responsibility for delays, it must award damages, regardless of any contractual prohibition or absence of a provision for damages.

The court further stated that in situations where the contract inadequately restricts or fails to provide remedies for the contractor to claim damages, the arbitral tribunal has the authority to go beyond the contract’s boundaries to grant the relief that the party is legally entitled to.

Regarding the rejection of certain claims, the court upheld the tribunal’s decision on the denial of claims related to damage to reputation, costs of arbitration, and the interest component. It reasoned that the petitioner failed to prove reputational loss due to the agreement’s termination, and the initiation of insolvency proceedings could not be entirely attributed to the termination.

The court noted that the agreement constrained the tribunal from awarding costs to any party, and it prohibited anti-lite and pendente lite interest. It emphasized that the tribunal, as a creation of the contract, is bound by reasonable restrictions on its power imposed by the agreement.

In addressing the issue of partial setting aside of the award, the court clarified that severing the findings on claims 3 and 4 from the rest of the award does not constitute a modification of the award. It explained that modification would involve altering damages awarded or changing the interest rate. Setting aside unconnected or independent findings of the tribunal does not amount to modifying the award. Consequently, the court set aside the award on claims 3 and 4, remitting them back to the tribunal for fresh consideration.

“PRIME LEGAL is a full-service law firm that has won a National Award and has more than 20 years of experience in an array of sectors and practice areas. Prime legal fall into a category of best law firm, best lawyer, best family lawyer, best divorce lawyer, best divorce law firm, best criminal lawyer, best criminal law firm, best consumer lawyer, best civil lawyer.”

Written by- Afshan Ahmad

Click here to read the judgement

0

Patent Illegality, Patent Injustice, Redefining Fairness in Award Review: Delhi High Court

Case Title: MBL Infrastructures Limited vs Delhi Metro Rail Corporation

Case No: 12/12/2023

Decided on: O.M.P. (COMM) 311/2021

Coram: The Hon’ble Mr. Justice Chandra Dhari Singh

 

 Facts of the Case

MBL Infrastructure Ltd., a civil engineering company, entered into a contract with Delhi Metro Railway Corporation in 2012 to construct Sarai Metro Station in Delhi. The project, valued at Rs. 41.57 crore, was meant to be completed within 18 months. However, disputes arose due to alleged delays in site handover by the Metro and non-compliance by MBL. The Metro terminated the contract and encashed bank guarantees in 2013. Arbitration in 2015-2020 found the Metro responsible for delays and the termination illegal, but rejected MBL’s claims for damages and profits. MBL filed a petition challenging this partial award. The case hinges on proving who caused the project’s downfall. The court will determine whether the arbitration tribunal’s decision on specific claims was legally sound.

Legal Provision

Section 34 of the Arbitration and Conciliation Act, 1996 provides for the grounds of setting aside an arbitral award.

 (1) Recourse to a Court against an arbitral award may be made only by an application for setting aside such award in accordance with sub-section (2) and sub-section (3).

(2) An arbitral award may be set aside by the Court only if—

(a) the party making the application [establishes on the basis of the record of the arbitral tribunal that]—

(i) a party was under some incapacity; or

(ii) the arbitration agreement is not valid under the law to which the parties have subjected it or, failing any indication thereon, under the law for the time being in force; or

(iii) the party making the application was not given proper notice of the appointment of an arbitrator or of the arbitral proceedings or was otherwise unable to present his case; or

 (iv) the arbitral award deals with a dispute not contemplated by or not falling within the terms of the submission to arbitration, or it contains decisions on matters beyond the scope of the submission to arbitration: Provided that, if the decisions on matters submitted to arbitration can be separated from those not so submitted, only that part of the arbitral award which contains decisions on matters not submitted to arbitration may be set aside; or

(v) the composition of the arbitral tribunal or the arbitral procedure was not in accordance with the agreement of the parties, unless such agreement was in conflict with a provision of this Part from which the parties cannot derogate, or, failing such agreement, was not in accordance with this Part; or (b) the Court finds that— (i) the subject-matter of the dispute is not capable of settlement by arbitration under the law for the time being in force, or (ii) the arbitral award is in conflict with the public policy of India.

Section 73 of the Indian Contract Act, 1872 provides compensation for the loss or damage caused by the breach of Contract.

Issue

  1. Whether the learned Tribunal has erred in not awarding the damages to the petitioner despite holding that the delay is attributable to the respondent?
  2. Whether Arbitral tribunal can go beyond to grant relief to aggrieved party when contract illegally restricts Remedies?
  3. Whether DMRC’s actions caused significant delays and if MBL deserves compensation for their alleged losses?

Court Decision and Analysis

In light of the precedents set by the judgements in cases like, NHAI v. Trichy Thanjavur Expressway Ltd. 2023 SCC Del 5183, Union of India v. Alcon Builders & Engineer (P) Ltd 2023 SCC OnLine Del 160, and few more, the Court found itself empowered under Section 34 of the Act to rectify specific parts of the arbitration award that are demonstrably flawed and fundamentally unjust. Such portions must be so blatantly erroneous that they shake the very foundation of this Court’s judicial conscience.

However, it is crucial to note that setting aside any portion of the award should not inadvertently impact the upheld sections. Any such action must be carefully executed to avoid unintended consequences or cascading effects that disrupt the remaining provisions.

Therefore, should the Court choose to set aside Claim No. 3 (Damages on Account of Idling of Machines and loss of overheads) and Claim No. 4 (loss of profit), it assured that the remaining claims will remain unaffected and suffer no adverse repercussions. This targeted approach upholds the valid aspects of the award while correcting the demonstrably problematic portions.

The Tribunal’s decision was legally flawed. They admitted respondent’s wrongful delays and contract termination, yet denied damages to the petitioner. This contradicts the law and ignores the unique circumstances of the case, where wrongful termination replaced a deserved extension.

The Award exhibited patent illegality due to the Tribunal’s inconsistency in Claim no. 1. While acknowledging the respondent’s project delays, they inexplicably withheld damages from the petitioner, rendering the Award legally unsound.

In view of the aforementioned claims, court partially allowed the petition and disposed pending applications.

“PRIME LEGAL is a full-service law firm that has won a National Award and has more than 20 years of experience in an array of sectors and practice areas. Prime legal falls into the category of best law firm, best lawyer, best family lawyer, best divorce lawyer, best divorce law firm, best criminal lawyer, best criminal law firm, best consumer lawyer, best civil lawyer.”

 

Written by- Bhawana Bahety

click to view judgement